Client Name: Mitchells & Butlers Project Location: The Navigation Inn, 4 Wharf Road, Enfield, EN3 4XX Duration of Project: 2 months Sector: Hospitality Service Provided: Excavation and installation of new drainage system Challenge: The Navigation Inn’s proximity to the River Lee makes it highly susceptible to flooding, particularly during periods of heavy rainfall. The surrounding...Continue reading→
Tree Root Removal Services for Storm Group
Sector: Public (Council owned day care)
Client: Storm Group
Project Location: Lion and Hogarth Centre, Brentwood
Duration of project: 3 weeks
London Drainage Facilities were approached by Storm Group to offer vital support for their project at the Lion and Hogarth Centre in Brentwood.
Challenge
The Lion and Hogarth Centre is a council-owned day centre for older people, providing care and a friendly, sociable environment to enjoy during retirement years. Unfortunately, the centre has experienced ongoing flooding and drainage issues over several years which have been problematic for the staff and day care community. Regular internal flooding has spoiled the facilities and routine at the centre. As a result, Storm Group contacted London Drainage Facilities to find a solution to this long-standing problem.
Solution
Our work began by using sophisticated CCTV technology to identify the ‘root’ of the problem. And in this case, it actually was tree roots that had spread and were affecting the drainage of the council property. Tree roots are one of the leading causes of blocked or cracked drains and they can cause significant problems with drainage if left to spread. A worst-case scenario can create overflowing manholes and even subsidence in a building, or problems with the foundations.
Roots are constantly growing as they seek out new sources of nutrients in soil, including water and oxygen. When pipes are laid beneath the ground, this often disturbs the soil around them, meaning that tree roots find it easier to grow along these paths. Where there are any slight cracks or leaks in pipework due to general wear and tear, tree roots can exploit these weaknesses and spread within them.
London Drainage Facilities quickly identified that tree roots were the cause of the issue. This identification allowed us to create an action plan to clear them and restore the property’s drainage system.
The next step was to use our powerful Picote machinery which is an effective way to cut through any blockages including concrete, tree roots and any other type of drain blockage. This equipment works by using twister brushes, along with a robust 3mm metal panel and a front drill head with star carbides. We carefully worked our way through the drain blockage, with regular CCTV resurveying beneath the ground to check on the progress. We also incorporated high pressure jet washing to flood water through the area as required, along with suction equipment to efficiently clear the roots.
The project was completed in just 3 weeks and has entirely resolved this ongoing issue at the Lion and Hogarth Centre in Brentwood, allowing the day care building to resume its activities.
Get in touch to find out more about our services
London Drainage Facilities are proud to be known as one of the leading drain repair providers operating in London and throughout the south-east. If you’re experiencing any related problems in your property, you can learn more about our services or book a callout by calling 0800 612 2179.
Plumbing Pipework Replacement and Drainage Clearance
Client Name: Mitchells & Butlers Project Location: The Globe, 83 Moorgate, London EC2M 6SA Duration of Project: 1 day (Sunday) Sector: Hospitality Service Provided: Plumbing pipework replacement and drainage clearance Challenge: The pipework serving the upstairs toilets was located within a ceiling void, making it completely inaccessible. Over time, the system had developed severe...Continue reading→
New Drainage Installation for Lower Ground Office Building in the UK
Location: 28 Bolton St, London, W1 8BP Project Dates: 1st July 2024 to 5th July 2024 Project Overview: This project entailed the installation of a new drainage system for a lower ground office building situated in central London. The three-story building has a total floor area of approximately 6,000 square meters. The lower ground floor,...Continue reading→
Rehabilitation of Underslab Drainage System at Amersham Place
Client Overview: Global Life Sciences Solutions Operations UK Ltd. is a prominent company operating in the life sciences sector. They own a facility located at Amersham Place, Little Chalfont HP7 9NA, where they conduct various operations critical to their business. Background: The underslab drainage system at the Amersham Place facility required urgent attention due to...Continue reading→
Lewisham Park Towers
Project Overview: Lewisham Park Towers is undergoing a comprehensive regeneration project aimed at enhancing the infrastructure and living conditions within the site. The project encompasses three towers, involving the complete replacement of exterior cladding, internal refurbishments of kitchens and bathrooms, and the relocation of soil stacks. The scope of work also includes the installation of...Continue reading→
Repair Work to Sheerness Dockyard Church on behalf of Coniston Ltd
Sector: Construction Client: Coniston Ltd Project Location: Sheerness Dockyard Church Duration of project: 1 month London Drainage Facilities were approached by Coniston Ltd, who are contractors on the largescale Sheerness Dockyard Church renovation at Sheppey, Kent. Challenge The original Sheerness Dockyard Church was badly damaged by fire back in 2001. The building stands at the...Continue reading→
Tanker and Wet Vac Services To Clear House of Commons Flood
Sector: Facilities Management Client: House of Commons Project Location: House of Commons, Palace of Westminster Duration of project: 1 week London Drainage Facilities responded to a flash flooding emergency at the House of Commons, following a prolonged stretch of downpours and storms. We provided tanker and wet vacs services to clear the flood and restore this high-profile...Continue reading→
Tanker and Wet Vac Services to Combat Flash Flooding at Newham General Hospital
Sector: Facilities Management Client: KRH Contracts Ltd Project Location: Newham General Hospital, Glen Road, London, E13 8RU Duration of project: 1 night When extreme weather hits the UK, this can be damaging and chaotic for public services. London Drainage Facilities were contacted after Newham General Hospital in East London was forced to close its busy A&E department due...Continue reading→
Picote Concrete Removal for BAM Nuttall Ltd at Heathrow Airport
Sector: Commercial Client: BAM Nuttall Ltd Project Location: Heathrow Airport Tunnels Duration of project: 1 month London Drainage Facilities were delighted to win the tender for a ground-breaking project at Heathrow Airport. Our client, BAM Nuttall Ltd, had been working there since 2014, upgrading the main tunnel into the Heathrow central terminal area. The client...Continue reading→