Client Name: Mitchells & Butlers Project Location: The Navigation Inn, 4 Wharf Road, Enfield, EN3 4XX Duration of Project: 2 months Sector: Hospitality Service Provided: Excavation and installation of new drainage system Challenge: The Navigation Inn’s proximity to the River Lee makes it highly susceptible to flooding, particularly during periods of heavy rainfall. The surrounding...Continue reading→
Rehabilitation of Underslab Drainage System at Amersham Place
Client Overview:
Global Life Sciences Solutions Operations UK Ltd. is a prominent company operating in the life sciences sector. They own a facility located at Amersham Place, Little Chalfont HP7 9NA, where they conduct various operations critical to their business.
Background:
The underslab drainage system at the Amersham Place facility required urgent attention due to various issues affecting its functionality. To address this, the client engaged our team of professionals to conduct a comprehensive CCTV survey of the drainage system to identify any underlying problems.
Scope of Work:
London Drainage Facilities commenced the project by conducting a thorough CCTV survey of all accessible underslab drainage across the site. This involved deploying specialised equipment and trained personnel to inspect the entire drainage network for any defects, blockages, or damages.
Upon completion of the survey, it was evident that extensive repair works were necessary to restore the drainage system to its original state. The identified issues included the need for lining, patching, cleaning/descaling and root cutting.
The repair process involved the following steps:
Cleaning/Descaling and Root Cutting: Utilising specialist Picote machinery, the team conducted cleaning, descaling and root cutting operations to prepare the pipes for repair.
Lining and Patching: Extensive lining and patching works were carried out on sections of the drainage system, involving the application of 100mm and 150mm lining and patching materials.
CCTV Inspection: For pipework sized at 225mm, a specialist Crawler Unit and a trained 3-man team equipped with confined space equipment were deployed to conduct CCTV inspections to ensure the integrity of the repaired sections.
Excavation and Replacement: In instances where sections of pipework were collapsed beyond repair, excavation works were undertaken by specialist teams. The damaged sections were replaced with BS-approved equivalents and backfilled to match the existing surface area.
Post-Repair Survey: Following the completion of all repair works, a comprehensive re-survey of all sections of pipework was conducted to verify that the repairs were executed correctly and to ensure the overall integrity of the drainage system.
Challenges:
Several challenges were encountered throughout the project, including the need for specialised equipment, confined space requirements for certain inspection tasks, and the complexity of the repair works due to the extent of damage to the drainage system.
Outcomes:
Despite the challenges faced, London Drainage Facilities successfully completed the rehabilitation of the underslab drainage system at Amersham Place. The repaired system now functions efficiently, ensuring uninterrupted operations at the client’s facility and mitigating the risk of future drainage issues.
Conclusion:
The project exemplifies London Drainage Facilities’ expertise in providing comprehensive drainage solutions, addressing complex issues with precision and efficiency. By successfully restoring the underslab drainage system, the project has contributed to the seamless operation of the client’s facility and has enhanced its infrastructure resilience.
Plumbing Pipework Replacement and Drainage Clearance
Client Name: Mitchells & Butlers Project Location: The Globe, 83 Moorgate, London EC2M 6SA Duration of Project: 1 day (Sunday) Sector: Hospitality Service Provided: Plumbing pipework replacement and drainage clearance Challenge: The pipework serving the upstairs toilets was located within a ceiling void, making it completely inaccessible. Over time, the system had developed severe...Continue reading→
New Drainage Installation for Lower Ground Office Building in the UK
Location: 28 Bolton St, London, W1 8BP Project Dates: 1st July 2024 to 5th July 2024 Project Overview: This project entailed the installation of a new drainage system for a lower ground office building situated in central London. The three-story building has a total floor area of approximately 6,000 square meters. The lower ground floor,...Continue reading→
Lewisham Park Towers
Project Overview: Lewisham Park Towers is undergoing a comprehensive regeneration project aimed at enhancing the infrastructure and living conditions within the site. The project encompasses three towers, involving the complete replacement of exterior cladding, internal refurbishments of kitchens and bathrooms, and the relocation of soil stacks. The scope of work also includes the installation of...Continue reading→
Repair Work to Sheerness Dockyard Church on behalf of Coniston Ltd
Sector: Construction Client: Coniston Ltd Project Location: Sheerness Dockyard Church Duration of project: 1 month London Drainage Facilities were approached by Coniston Ltd, who are contractors on the largescale Sheerness Dockyard Church renovation at Sheppey, Kent. Challenge The original Sheerness Dockyard Church was badly damaged by fire back in 2001. The building stands at the...Continue reading→
Tanker and Wet Vac Services To Clear House of Commons Flood
Sector: Facilities Management Client: House of Commons Project Location: House of Commons, Palace of Westminster Duration of project: 1 week London Drainage Facilities responded to a flash flooding emergency at the House of Commons, following a prolonged stretch of downpours and storms. We provided tanker and wet vacs services to clear the flood and restore this high-profile...Continue reading→
Tanker and Wet Vac Services to Combat Flash Flooding at Newham General Hospital
Sector: Facilities Management Client: KRH Contracts Ltd Project Location: Newham General Hospital, Glen Road, London, E13 8RU Duration of project: 1 night When extreme weather hits the UK, this can be damaging and chaotic for public services. London Drainage Facilities were contacted after Newham General Hospital in East London was forced to close its busy A&E department due...Continue reading→
Picote Concrete Removal for BAM Nuttall Ltd at Heathrow Airport
Sector: Commercial Client: BAM Nuttall Ltd Project Location: Heathrow Airport Tunnels Duration of project: 1 month London Drainage Facilities were delighted to win the tender for a ground-breaking project at Heathrow Airport. Our client, BAM Nuttall Ltd, had been working there since 2014, upgrading the main tunnel into the Heathrow central terminal area. The client...Continue reading→
Tree Root Removal Services for Storm Group
Sector: Public (Council owned day care)Client: Storm GroupProject Location: Lion and Hogarth Centre, BrentwoodDuration of project: 3 weeksLondon Drainage Facilities were approached by Storm Group to offer vital support for their project at the Lion and Hogarth Centre in Brentwood.ChallengeThe Lion and Hogarth Centre is a council-owned day centre for older people, providing care and...Continue reading→