During works: After works:
After recently attending an emergency call from a central London School, our engineers were quick to diagnose the cause of the blockage as broken section of pipe work which had begun to colapse. Unfortunatley the location of the broken drain was beyond a foundation wall in the caretakers office. We were instructed to carry out a manual drain repair by means of excavation, which required a tunelling team. Works commenced early on a Saturday morning and with four very commited engineers working as a great team, the drainage system was up and running late Sunday evening, allowing the School to re-open as normal Monday.